| Setup parameter | Typical value | Effect if wrong |
|---|---|---|
| Roll gap at last station | Coil thickness plus 0.05 to 0.15 mm | Spring back, camber, uneven flange |
| Roll axis offset | Under 0.5 mm across stations | Twist that changes along the length |
| Frame levelness | Under 1 mm over machine length | Bow under load |
| Punching method | Practical line speed | Holes per minute at 2 inch pitch |
|---|---|---|
| Hydraulic punch | 3 to 4 m/min | 118 to 158 |
| Mechanical press punch | 10 to 15 m/min | 394 to 591 |
| Rotary punch | 30 plus m/min | 1,180 plus |
| Check | Tool | Acceptance |
|---|---|---|
| Section height | Height gauge | Drawing tolerance, typically plus or minus 0.5 mm |
| Hole position along length | Tape or laser | Plus or minus 0.5 mm over 6 m |
| Hole pitch | Vernier | Pitch plus or minus 0.2 mm |
| Straightness | Straight edge and feeler | Under 3 mm over 6 m |
| Twist | Straight edge on flat surface | Under 2 degrees per metre |
Q: How long does upright rack machine setup take on a new line?
Q: What is the most common mistake in upright rack machine setup?
Q: Do I need laser alignment during upright rack machine setup?
Q: How tight should hole position be after upright rack machine setup?
Q: Should I run the first off at full speed to prove output?
Q: What steel grade makes upright rack machine setup easiest?
Short answer Cable tray cut off is the step that...
Read MoreShort answer Upright punch die life is the number of...
Read MoreCable Tray Auto Stacking: Bundle, Nest and Container Loading Short...
Read MoreOld Upright Line Retrofit: Servo Punching and Double-Side Dies Short...
Read More